Converting tonnes to cubic metres for earthworks

Volume in cubic metres is tonnes divided by density in tonnes per cubic metre. The hard part is using the right density.

The formula

Cubic metres = tonnes ÷ density (t/m³)

And the other way: tonnes = cubic metres × density.

A worked example

A truck carries 42 tonnes of material with a loose density of 1.8 t/m³.

42 ÷ 1.8 = 23.3 loose cubic metres in the tray.

The 1.8 here is an example figure. Use the density from your own geotechnical report or site testing.

Bank, loose and compacted

The same material has three volumes, so it has three densities.

  • Bank is the material in the ground, before it is dug.
  • Loose is the material in the truck. It has swelled, so the same tonnes take up more room.
  • Compacted is the material placed and rolled in the fill.

A design quantity is usually bank or compacted. A truck measures loose. Convert tonnes with the density that matches the volume you are reporting, or convert loose volume with a swell or compaction factor from your testing.

Estimating loads remaining

Loads remaining = tonnes remaining ÷ expected tonnes per load

A work order has 5,000 tonnes left. The trucks carry an expected 45 tonnes.

5,000 ÷ 45 = 111.1, so 112 loads.

If the target is in cubic metres, convert it to tonnes first with the density, then divide.

Common mistakes

  • Using one density for every material on site.
  • Mixing bank and loose volumes in the same report.
  • Using the truck's rated payload when the trucks are running under it.
  • Not recording the date a density changed after new test results.

How Eaglite does it

In Eaglite each material has a density, a compaction factor and the date they apply from. Tonnes the operator types are converted to cubic metres for the work order, and volume targets are converted back to an estimate of loads remaining. More on earthworks tracking with Eaglite.

Show us one project.

We get to know the projects you run, show you Eaglite, and tell you straight whether it fits. The quote comes after.

Not sure yet? Start with a 14-day pilot

From $19 a day per machine, ex GST.