Guide
Load and haul cycle time, and how to measure it
Cycle time is the time a truck takes to get from one load to the next. It decides how many loads a fleet moves in a shift.
What is in a cycle
One cycle is the sum of five parts:
- Queue and spot at the loading unit.
- Load.
- Haul to the dump.
- Dump, including any wait.
- Return.
From cycle time to production
Loads per hour for one truck = 60 ÷ cycle time in minutes
Tonnes per hour for the fleet = trucks × loads per hour × tonnes per load
A worked example
A truck's cycle is 20 minutes. 60 ÷ 20 = 3 loads an hour.
Four trucks at 40 tonnes a load: 4 × 3 × 40 = 480 tonnes an hour.
Cut the cycle to 18 minutes and the same four trucks move 533 tonnes an hour. Two minutes a cycle is 53 tonnes an hour.
These are example figures. The sum assumes the loading unit can keep up and the trucks do not queue.
How to measure it
- Stopwatch study. Ride with a truck or stand at the loading unit for an hour. Accurate for that hour, and it takes a person.
- From load records. If every load is recorded with its time, the gap between one load and the next is the cycle. You get every cycle for every truck, every shift.
What to look for
- One truck with a longer cycle than the others on the same run.
- Cycles that stretch through the shift.
- Loads per hour that drop after a break.
- Trucks bunching, which shows up as queue time at the loading unit.
How Eaglite does it
Eaglite stores a time with every load and dump, so the dashboard shows each operator's loads and cycle times and the loads per hour for the shift. Eaglite's cycle time runs from the load press to the dump press, the loaded leg. The empty return is not counted in it. See the dashboard and shift review.